Site Reports: Overseas

Dongguan Changan Huanan Electronics Factory
Dongguan Changan Huanan Electronics Factory
Dongguan Changan Huanan Electronics Factory
Location Zhenan Hi-teck Industrial park, Dongguan City, Guangdong Province, People's Republic of China
Production Coils, Ferrite Magnets, NEO-REC Magnets, EMC Center
Land 89,654 square meters
Premises 52,623 square meters
Completion September 2001
Contents
Description of the Sites and Its Policy
FY 2007 Targets and Results
FY 2007 Environmental Activities
Communication with Local Communities
Environmental Burden Data
Description of the Site and Its Policy
Environmental Policy-Dongguan Changan Huanan Electronics Factory
Our Philosophy
The Huanan Electronics Factory shall conduct activities in pursuit of a recycling-oriented society by paying comprehensive attention to environmental protection, as well as energy and resource conservation.
Our Policy
1. We shall comply with all relevant national, local environment-related laws, regulations, and requirements set by our clients;
2. We shall establish a sound environmental management system, set and implement relevant indices and goals and achieve continuous improvement;
3. We shall securely control chemical substances to prevent environmental pollution;
4. We shall strive to reduce energy consumption to prevent global warming;
5. We shall reduce waste emissions and encourage recycling for more efficient resource usage;
6. We shall educate our employees and others who engage in works on behalf of the Company, in order to make them more environmentally conscious and thus actively participate and cooperate in the environmental protection activities.
  Enacted September 1, 2003
Revised January 20, 2006
PAGE TOP
FY 2007 Targets and Results
Objectives Targets Results
Enhancement of environmental management systems Comprehensive implementation of ISO 14001: 2004 version of the environmental management system Pass the external audit held in early FY 2008 Evaluation of environmental elements was completed in March. The results were issued and publicized to all divisions in early April. An internal audit of the environmental management system and the management review were conducted in April. Successfully passed the external audit conducted on April 28 and 29.
Global warming prevention Reduction of diesel oil consumption for power generation For the full year: ratio of generated electricity to total electricity consumption below 25% For the full year: usage of generated electricity was 6,270,500 KWH, accounting for 23% of total electricity consumption of 27,250,280KWH, achieving the target for the full year, achieving the target for the year.
Reduction of diesel oil consumption for domestic use For the full year: reduce usage of fuels by 18% or more from the previous year Fuel consumption for FY 2006: 192,600L
Fuel consumption for FY 2007: 142,874L
Reduced by 25.8% in total (achieved the target for the full year)
Emission control Reduction of water discharge Planned reduction of water discharge for the full year: 10,000 tons Usage of recycled water for the full year: 11,201 tons (target achieved)
Reduce material edges of the RM division Amount of material edges for disposal from 1kg of raw materials: 0.1485 kg/kg Amount of material edges for disposal from 1kg of raw material was 0.13312 kg/kg for the fourth quarter (target achieved)
Environmental
risk management
Achieving the standard for BOD/COD of domestic wastewater Monitoring by external organization
BOD<2
COD<90
Conducted monthly monitoring for 12 months, of which 11 months met the emission standard.
In a survey conducted in January 2007, BOD value reached 64 while COD to 259, failing to meet the requirements due to a block in the sewage lines during the construction of a new plant building. After the implementation of countermeasures, BOD and COD values met the requirements in February and March.
Achievement of discharge standard for NEO electroplating wastewater 1. Achieve 100% pass rate of emission value for pH at the outlet of wastewater station
2. Achieve 100% pass rate of weekly voluntary inspection
3. Achieve 100% pass rate of external inspection
4. Achieve 100% pass rate of the inspection conducted by the Environmental Protection Agency
1. Achieved 100% pass rate of emission value for pH at the outlet of wastewater station
2. Achieved 100% pass rate of weekly voluntary inspection
3 .Achieved 100% pass rate of external inspection
4. Achieved 100% pass rate of the inspection conducted by the Environmental Protection Agency
PAGE TOP
FY 2007 Environmental Activities
Resource Saving: Reduction of IPA usage
1. Resource Saving: Reduction of IPA usage

An automatic cleaning line for electroplating was introduced in the electroplating process at the NEO production division in January 2008. This significantly contributed to the reduction of IPA, achieving an average 30% reduction for 10 months.
Energy-Saving: Reduction of Diesel Oil Usage
2. Energy-Saving: Reduction of Diesel Oil Usage

At the end of March 2008, our solar energy facilities at former dormitories marked the 1st anniversary of its operations that started in April 2007. The facilities worked without problem, successfully reducing diesel oil consumption by 49,726 kg, which is equivalent to approx. 320,000 yuan in 2007, compared with the diesel oil consumed by fuel-operated boilers in FY 2006. At the same time the temporary cost to install solar energy water heating system, 300,000 yuan, was recovered.
Reduction of Wastewater Discharge
Reduction of Wastewater Discharge
3.Reduction of Wastewater Discharge

By adding K-material separator and filter pumps in processing at the WET manufacturing division, usage of recycled water increased, which reduced the wastewater discharge. Water for toilet flushing and greenery at the WET manufacturing sites was 100% recycled water. Recycled water was also used to clean roads on the plant site. This reduced 11,201 tons of water discharge a year, surpassing the targeted 10,000 tons.
PAGE TOP
Communication with Local Communities
Environmental Protection Activity 'We Love Lianhuashan' ----Collecting Trash in Lianhuashan of Changan
Environmental Protection Activity 'We Love Lianhuashan' ----Collecting Trash in Lianhuashan of Changan
1. Environmental Protection Activity "We Love Lianhuashan"
----Collecting Trash in Lianhuashan of Changan


According to plan, 42 people from various divisions of the Huanan Electronics Factory participated in the environmental protection activity entitled "We Love Lianhuashan" held in the morning of November 24. Participants starting climbing the mountain on foot at 9 a.m., with each individual carrying a plastic bag to pick up garbage on the mountain trail. The starting point was on the east edge of the mountain and the goal was to reach the west edge. All of them climbed down the mountain at around 11 a.m. The total amount of trash collected reached 85.34 kg. With the approval of the administrative office, the garbage bags was dumped at the waste storage site next to the parking lot. Our efforts were appreciated by the people at the administrative office.
 2. Tree planting at the Dam
 2. Tree planting at the Dam
2. Tree planting at the Dam

In March 2008, 46 employees of the factory participated in tree planting activities conducted in the Dam of Changan. They planted 68 saplings of the following varieties, increasing the number from 40 in the initial plan:
1. Aquilaria sinensis
2. Camphor tree
3. Hainan grapes
4. Chenopod
PAGE TOP
Environmental Burden Data
  • Atmosphere
  • Facility Substances emitted Substances emitted*1 Regulatory level Results
    Automatic soldering machine Sn and Sn compounds 8.5 0.398
    Toluene 40 0.85
    Benzene 12 0.22
    Nonmethane hydrocarbon 120 2.29
    Xylene 70 0.36
    Lead and lead compounds 0.7 0.0002
    Coating machine Toluene 40 3.89
    Methyl alcohol 190 4.95
    Acetone 1.75
    Vulcanization furnace Hydrogen sulfide 0.57
    Odor concentration 2,000 110
    Power generator A heavy oil Sulfur oxides 500 461
    Nitrogen oxides 120 101
    Smoke and dust 120 40.9
    Coating process Hydrogen chloride 100 1.87
    Nitrogen oxides 120 2.05
    Sulfate mist 35 1.15
    Crusher Powder dust 120 27.5
    Kitchen Sulfur oxides 500 376
    Nitrogen oxides 120 85.3
    Soot and dust 120 25.7
    Greasy fumes 2.0 1.82
    *Unit: mg/m3
  • Water Quality
  • Category Regulatory level Results
    pH 6.0∼9.0 7.21
    SS 60 42
    COD 90 74.5
    BOD 20 15.7
    Petroleum 5 2.52
    LAS 5 1.35
    Phosphate 0.5 0.41
    Cu 0.5 0.11
    Ni 1.0 0.07
    * Unit: No unit for pH; mg/liter for others
    * SS: Suspended solids in water
    * COD: Chemical oxygen demand
    * BOD: Biochemical oxygen demand
    * LAS: Linear alkyl benzene sulfonic acid